STEMWALL FOOTER DETAIL
NOTES
- Bottom
of footer must be at least 12” below finished grade.
- 5/8”
rebar in footer must be cold bent (not heated) around each corner and
splices must lap a minimum of 25 inches.
- Bend
vertical steel into footer a minimum of 10 inches.
- Bend
vertical steel into slab a minimum distance of 16 inches.
- Anchor
bolts must be a minimum size of 5/8” and embed at least 7” in concrete.
- Maximum
spacing of anchor bolts 32 inches on center.
- 3-inch
washer required for anchor bolts.
- If a
bond beam is provided with 1-#5 rebar, only cells with vertical steel need